Davao City Grants Tax Breaks to ₱48.9 Billion in Projects, Led by Therma South Coal Plant Expansion

The city waives local business taxes, property taxes and permit fees for several years in exchange for jobs, more power and a large new events venue.

Published · 8 min read

By Kaeleb Savon Heck

DAVAO DEL NORTE, Nov. 14, 2026 — Davao City has granted local tax breaks to three private projects worth a combined ₱48.96 billion, and almost all of that money is tied to one thing: a proposed expansion of the Therma South coal-fired power plant in Binugao, Toril, which city officials have been pressing to grow as electricity bills climb and a strong El Niño threatens the hydropower that much of Mindanao depends on.

The Davao City Investment Promotions Center (DCIPC) announced the approvals this week through the City Information Office. According to figures released by the city and reported by local outlets including Edge Davao, The Chronicle and News Fort, the three projects are Therma South Inc.'s power plant project, valued at ₱47.946 billion; DavCon Events Center's Davao Convention and Trade Center, valued at about ₱834 million; and a paid parking facility by Alsons Development and Investment Corporation, valued at about ₱181.3 million.

DCIPC head April Marie C. Dayap called the total one of the biggest investment values the city has been able to generate, and noted that it covers 2026 alone. Under incentives approved by the Davao City Investment Incentive Board, the three companies get a five-year exemption from local business taxes, a three-year exemption from real property taxes, and a five-year exemption from mayor's permit fees and other local licenses.

For residents, the deal is a trade. The city gives up some local taxes and fees for several years. In return, it is betting on jobs, more power supply and new tourism infrastructure, and on bigger tax collections once the incentive periods end.

What was approved

The power project dwarfs the other two. It accounts for about 98 percent of the combined value.

According to The Chronicle's report, the Therma South project would add 300 megawatts to the plant's existing 300 megawatts of capacity, and is expected to create at least 2,150 jobs, about 2,000 of them during construction. Earlier reporting has used slightly different numbers for the planned expansion. In October, Edge Davao quoted City Councilor Louie John Bonguyan as saying the plant was previously authorized to develop up to 620 megawatts, and that proposed Units 3 and 4 could add 320 megawatts, or 160 megawatts each. Mindanao Times reported in July that the City Council approved a Phase II of two 172-megawatt units back in March 2014. The final size will depend on the company's design and on regulatory approvals.

The Davao Convention and Trade Center is a tourism project. The Chronicle, citing the Tourism Infrastructure and Enterprise Zone Authority, reported that the planned 17,835-square-meter facility would hold up to 10,000 guests and serve meetings, incentive trips, conferences and exhibitions, an industry known by the acronym MICE. Once completed, it is expected to be the largest MICE venue in Davao City, and it is projected to create at least 430 jobs.

The third project is a paid parking facility by Alsons Development and Investment Corporation, which the city said is meant to respond to growing demand for parking as the number of vehicles rises.

The city's job estimates vary by outlet. DavaoNews, summarizing the City Information Office release, put the combined total at at least 2,580 jobs including construction work, while a Politiko Mindanao report said the projects were expected to generate more than 4,500 jobs. The project-level figures that appear across reports are the 2,150 jobs for Therma South and 430 for the convention center.

Why the city wants more power

The approval comes after months of pressure from the City Council over power costs.

Davao Light and Power Co., the city's electricity distributor, buys power from several sources, including hydroelectric plants and coal plants. When those contracts do not cover demand, it turns to the Wholesale Electricity Spot Market, or WESM, where prices can swing sharply. Councilors have argued that this spot market exposure is one reason bills have jumped.

In July, Mindanao Times reported that Councilor Diosdado Angelo Mahipus Jr. told a council session that Davao Light needs around 600 megawatts but contracts only 108 megawatts from Therma South under its existing bilateral agreement. At the same session, Atty. Alona Borromeo, head of corporate services for AboitizPower's Transition Business Group, said Therma South was running at full capacity, producing 300 megawatts gross and 270 megawatts net, and that about 92 percent of its net output was already contracted to 22 distribution utilities and electric cooperatives across Mindanao. She also explained that affiliate rules cap how much Davao Light can buy from Therma South, a sister company in the Aboitiz group, at 50 percent of its energy needs.

"More capacity, higher supply, more stable prices," Borromeo told councilors, according to Mindanao Times, while saying the company was still studying whether an expansion was viable.

By October, the council had passed resolutions asking Therma South to supply more power to Davao Light and to fast-track Units 3 and 4. Bonguyan told the city's Pulong Pulong para sa Dabawenyo program that the company was still conducting a feasibility study, with an update possibly in November or December, according to Edge Davao.

The weather has raised the stakes. Bonguyan warned in October that El Niño could push rates higher by cutting output from the Agus-Pulangi hydropower complex, which he said supplies almost half of the city's power through the Power Sector Assets and Liabilities Management Corporation. Less cheap hydropower means more buying from the spot market.

The coal question

Therma South's expansion is possible in part because of how the national coal policy was written.

In 2020, the Department of Energy adopted a moratorium on new coal-fired power plants. But the department later clarified that the policy does not cover existing, operating coal plants and their expansion plans, according to the department and industry outlet Power Philippines. That carve-out is what allows an existing site like Therma South's to grow while new greenfield coal projects are generally blocked.

That will not settle the debate. Coal provides steady baseload power that does not depend on rainfall, which is exactly what city officials say they want during a drought year. It is also the most carbon-intensive way to make electricity, and an expansion approved now could run for decades. City officials have framed the project almost entirely around supply and price. The incentive announcement did not address emissions or air quality, and none of the reports reviewed for this article described a public timeline for environmental permitting of the new units.

Analysis: what Davao gets, and what it gives up

The incentive package is not a subsidy paid out of the city treasury. It is revenue the city chooses not to collect for a set number of years. Dayap argued that the city will come out ahead because of jobs and future revenue. "While they invested now, in the future the revenue generation for the city will also be substantial," she said, according to a translation published by News Fort, adding that employment is the mayor's focus.

How good the deal is will depend on details that have not been made public, including the exact tax value being waived and whether the power project is built on the schedule the city hopes for. Large power projects in the Philippines often take years to move from feasibility study to commercial operation, and the expansion still needs a final investment decision from the company as well as national permits.

There is also the question of who benefits from the power. A bigger plant does not automatically mean cheaper bills in Davao City. Under the affiliate cap described by AboitizPower, Davao Light can only source up to half its needs from Therma South, and any new supply contracts would go through competitive selection and regulatory review. More supply on the Mindanao grid could still ease spot market prices during tight periods, which is the argument the company and the council have made.

For the convention center, the case is more straightforward. Davao has been trying to draw more conferences and events, and a venue for 10,000 people would give it room to compete for larger gatherings. That would matter to hotels, restaurants and transport operators well beyond the venue itself.

What's next

  • Therma South's decision: The company has said its feasibility study is ongoing. Watch for an announcement on whether it will build the new units, their final size and a target date.
  • Permits and contracts: Any expansion will need national regulatory approvals, and any new power supply deal with Davao Light would go through competitive selection and the Energy Regulatory Commission.
  • More investments: Dayap said interest is rising, especially in property development, and that more projects are expected in 2027.
  • Power bills: With El Niño expected to stretch into next year, residents will be watching monthly rate adjustments from Davao Light, which councilors have said depend heavily on how much power is bought from the spot market.

Sources

  • The Chronicle, "Davao City approves incentives for P48.9 billion in investments": https://thechronicle.com.ph/davao-city-approves-incentives-for-p48-9-billion-in-investments/
  • DavaoNews, "Davao City grants incentives to three projects worth P48.9 billion": https://davaonews.com/news/p48-9b-in-investments-approved-in-davao-city-yy4uak
  • News Fort, "P48.9B in investments approved in Davao City": https://newsfortph.com/top-stories/p48-9b-in-investments-approved-in-davao-city
  • Politiko Mindanao, "Davao City gov't OKs nearly P48.9B in fresh investments": https://mindanao.politiko.com.ph/davao-city-govt-oks-nearly-p48-9b-in-fresh-investments/
  • Edge Davao, "Davao City pushes cheaper power from TSI, eyes 320-MW expansion to curb power costs": https://edgedavao.net/latest-news/2026/10/davao-city-pushes-cheaper-power-from-tsi-eyes-320-mw-expansion-to-curb-power-costs/
  • Mindanao Times, "TSI conducts feasibility study for Phase 2 development": https://www.mindanaotimes.com.ph/tsi-conducts-feasibility-study-to-expand-generation-capacity/
  • Power Philippines, "DOE excludes existing plants' expansion plans from coal moratorium": https://powerphilippines.com/doe-excludes-existing-plants-expansion-plans-from-coal-moratorium/
  • Department of Energy, "Clarification on the coverage of the coal moratorium policy": https://legacy.doe.gov.ph/press-releases/clarification-coverage-coal-moratorium-policy

Return to all Chronicle publications

Continue reading

No saved reading progress on this device.

Keep the connection.

LET’S MAKE
SOMETHING. ↗

Listen

Playback and availability are provided by Apple Music.